We had orientation on Thurs. We closed on Fri. And, we're starting to move things in today! We are beyond excited about this house. It is perfect for us and our family. A big thank you to Ruthie for all of your help. We can't wait to have you up when we have furniture in!!
We have a busy week ahead of us. We will be moving all the small boxes and items we can in Sat., Sun., and Mon. The movers will be coming Tues. to move all of the furniture in and take it into the house. We are planning on spending our first night in the house on Fri. the 4th. It's going to be very bittersweet leaving the Walker's house. We really want to take our time settling in. Feel free to stop by and visit anytime!!
Saturday, August 29, 2009
Monday, August 24, 2009
8-22-09 Applicances

They put on the corbles on the porch. The garage doors have caps on the top. The front door needs to be finished.





Tuesday, August 18, 2009
9-18-09 Home stretch
We are so close to completion! I'll be posting images from the last week. I'm hoping everything will be complete by the end of the week. I drove by this AM, and they have delivered the appliances. At this point, the "punch list" is all that needs to be done. Small repairs and touch ups. The landscaping has been put in, and the sod still has to be placed in the back yard as well.
Elle's showing off her twirls!
The girls' bathroom
carpet and hand rails
Countertops!
cabinets... they gave us a silverware holder!
The garage is finished
the landscaping was put in
1 of 2 trees
counter tops installed
counter tops-sink & breakfast bar
the On Cue system is wired
washer & dryer installed!













Monday, August 10, 2009
8-10-09 Avery & Updates

We have had the MOST important edition to the house this week! Our baby Avery has joined the Folzenlogel clan. So, I've gotten a little behind on posting; hopefully having a baby is a good enough excuse!!
Dave sent us this email (Fri 8-7):
…Get the grade set on the lot…Landscaping is scheduled for the 17th…Finish grade will be done and sod right after…We will rake yard of large rocks trash so you should not feel the remaining ones…The grade in the rear will not change much from what it is now…Will do our best
…Get porch corbels installed
…Get gutters installed
…Finish brick at porch
…Get window head-sets installed Scheduled work for next week… …8-7…Carpet
…8-10…Interior trim punch
…8-11…Drywall touch ups
…8-13…Clean …Ceiling at entry was repaired…Texture needs to be finished…
…Garage door panel will be replaced
…Have been working on the water heater this week…Office and p.o. issue…Will be changed as soon as possible
…Cabinets in kitchen will be touched up as we progress into the punch out stage
…Closet shelving will be added….
Dave the construction manager sent us this email today (Mon 8-10):
…Our painter always put the final coat of paint on after the carpet is laid…The final product is much better
…No corbel against the home
The wrong size water heater was installed (50 gal instead of 70)…Office is still working on…I checked with my plumber to see if he had received revised p.o.’s as yet and he had not
…The ceiling repair was a stress crack
…I do not set the orientations…I should be making the master punch list late this week…If you want we can walk late next week
…Will have to check on the window issue
…You will have a very short window on the yard…Finish grading is done first and sod ect is right behind…As I said this is schedules for Monday…We are doing four lots in SAE this day…I need to get the rough grade first and I hope that is this week…That is the best time line I can give…
We have a mailbox!


The laundry tub and plumbing.







Sunday, August 2, 2009
8-1-09 Cabinets

They installed the marble counter tops in the bathrooms.